| MassDOT Highway Division | ![]() |
|
|
|
![]() |
|
|
The Route 24 Interchange 8B project was funded by the American Recovery and Reinvestment Act of 2009 (ARRA), a critical component of the Patrick-Murray Administration's Massachusetts Recovery Plan to build transportation systems critical to job creation and lasting economic development in communities across the Commonwealth. The project has constructed Interchange 8B, in Freetown, Massachusetts between the existing exits 8 and 9. The goals of the project included reducing congestion at Exits 8 and 9 and on South Main Street while providing access to the new Fall River Executive Park. Elements to the project were constructed in Fall River. Achieving these goals required that several construction efforts were clustered together under a single project. Major components of this project included:
There were several possible options reviewed prior to selecting the preferred alternative that could have achieved the needs laid out above. The selected option does not result in the taking of any homes or businesses and required only minor strip takings of land. The project area also contains sites of general historic significance and particular importance to the Wampanoag Tribe of Aquinnah and the Mashpee Tribe. All of these sites were surveyed by the project’s archaeological consultants, flagged and fenced to ensure that they were not damaged by construction activities. Tribal Historic Preservation Officers from both tribes were involved in the design process and visited the sites during construction to monitor their wellbeing. A Design/Build Project To speed construction, work preceded using design/build methods. In traditional building projects, one firm is responsible for creating a design which is then put out to bid for construction. In a design/build process, the same team is responsible for designing and constructing a structure. This approach allows a project to be completed with greater speed and often at lower cost. In the case of the Route 24 Interchange 8B project, use of design/build methods allowed the project to be completed almost a year ahead of schedule. Timeline Notice to proceed for this project was granted by MassDOT Highway Division in November of 2009. The project fully opened to traffic in January, 2012. Both 2010 and 2011 were busy years for the Exit 8B project. Major components of the two construction years were as follows: Year 2010:
Year 2011:
To see a graphic of how all of these project elements were completed over the life of the project, please click here.
|
|
|
Copyright © 2012
Commonwealth of Massachusetts
|
|